GridAI produces 100 MMcf/d of natural gas and 14.5 million gallons of water a day, with two fiber carriers 3.5 miles away. 600 MW of gas is at the wellhead now, with a development path to be a multi-GW campus.
The Energy Park sits inside GridAI’s existing Powder River Basin operations.
GridAI is developing generation at the Energy Park using natural gas produced from the surrounding field. First power is planned behind the meter and does not rely on a large-load grid interconnection.
At a 9,500 Btu/kWh reference heat rate, 600 MW of continuous generation requires approximately 137 MMcf/d of gas. GridAI produces 100 MMcf/d today.
3,200 producing gas wells and 450 miles of pipeline.
Behind-the-meter generation using GridAI gas.
GridAI controls the Energy Park site through existing surface use agreements. Further land arrangements are in progress.
Produced today and handled through the field water system.
Dedicated high-capacity campus fiber still needs to be built.
Additional grid access is under development and is not required for the planned behind-the-meter first-power configuration.
GridAI reports 3P reserves of 1.9 Tcf, evaluated by Netherland, Sewell & Associates under SPE-PRMS with an effective date of 30 June 2025. Current production of 100 MMcf/d supports approximately 400 MW at the reference heat rate. The 600 MW target, and growth beyond it, requires additional field development through returning wells to production, recompletions and new drilling.
Campbell County, Wyoming
44.17979 N, 105.86604 W
ERCOT is tracking approximately 474 GW of large-load interconnection requests. About 90% are data centers. ERCOT’s all-time peak demand is 91.1 GW, set on 22 July 2026, against a normal range of 40 to 80 GW. The queue is about five times the largest load the grid has ever served.
GridAI’s first-power plan is different. Generation is developed on site using gas produced from the field.
Source: ERCOT, July 2026. Peak load per EIA.
Sources. Operator data: GridAI operator GIS database, August 2026, and operator-reported production. Transmission, substations and gas pipelines: HIFLD. Generation inventory: EIA-860. Carrier facilities and autonomous system numbers: PeeringDB. Climate: NOAA 1991 to 2020 normals. Tax provisions: Wyoming Business Council, W.S. §39-15-105 and §39-16-105. ERCOT large-load interconnection queue volume: ERCOT, July 2026. ERCOT all-time peak hourly load and normal operating range: ERCOT hourly load data; peak of 91.1 GW on 22 July 2026 as reported by the U.S. Energy Information Administration.
Basis of presentation. Volumes are operator-reported and are produced today unless labeled otherwise. Generation capacity and dates are targeted and reflect GridAI’s current development plan, subject to field development, equipment delivery, permitting and the timing of a signed offtake. The Energy Park site is controlled through existing surface use agreements, and further land arrangements are in progress and confirmed in diligence. Grid capacity and timing are indicated by Powder River Energy Corporation and Basin Electric Power Cooperative and remain subject to utility studies and written confirmation. Carbon capture and additional generation technologies are under evaluation. Distances are straight-line from the Energy Park coordinate. Fiber corridors are indicative alignments along Interstate 90 and are not surveyed cable routes. Nothing on this site constitutes an offer, a commitment, or a reserve report. Reserves are as reported by Netherland, Sewell & Associates under SPE-PRMS with an effective date of 30 June 2025; 3P is the least certain category and proved reserves are a small fraction of it. Gathering and distribution mileage described as mapped is drawn geometry from the operator GIS and includes lines that are not in service.
Send us the target MW at first energization, ramp schedule, ultimate campus size, target energization date and cooling approach. We will map the generation, gas, water and site plan around it.