Connectivity

Two carriers on the Interstate 90 corridor.

Range / Advanced Communications Technology and Visionary Broadband operate along Interstate 90, approximately 3.5 miles north of the Energy Park.

What exists

What exists today.

3.5 milesEnergy Park to I-90 fiber corridor
2Carriers on the corridor
3Carrier-neutral facilities within 70 miles
10.4 milesGridAI field fiber

GridAI’s existing fiber serves field telemetry and control. A hyperscale data center will require a dedicated high-capacity build.

What needs to be built

What still needs to be built.

The campus will require a purpose-built lateral and high-strand-count capacity sized to the tenant’s requirements. The route, strand count and diversity plan will be developed with the carriers.

Three inputs define the fiber build.

Strand count

Required capacity at first energization and full build.

Diversity

Required number of physically separate routes.

Latency

Required peering points and maximum latency.

Carrier facility locations and autonomous system numbers are from PeeringDB. No public route-level geometry exists for either carrier, so the corridor drawn on the maps is an indicative alignment along Interstate 90 rather than a surveyed cable route.

Next step

Start with the load.

Send us the target MW at first energization, ramp schedule, ultimate campus size, target energization date and cooling approach. We will map the generation, gas, water and site plan around it.