GridAI is developing modular gas-fired generation using natural gas produced from the field. Kodiak Power Solutions is the contracted generation partner.
The current plan uses modular reciprocating generation fueled by GridAI production and configured for behind-the-meter service to the Energy Park.
Generation above 600 MW requires additional gas production from the existing field development inventory.
| Basis | Value |
|---|---|
| Gas production today | 100 MMcf/d |
| Heat rate | 9,500 Btu/kWh |
| Gas per 600 MW | ~137 MMcf/d |
| Gas per 1 GW | ~228 MMcf/d |
| 3P reserves, NSAI, 30 June 2025 | 1.9 Tcf |
Current production of 100 MMcf/d covers approximately 400 MW at the reference heat rate. The 600 MW target and gigawatt-scale generation require additional field development.
Air permitting is being sequenced with the generation build. Current permit status and environmental work are available through project diligence.
The planned first-power configuration is behind the meter. GridAI is separately working with Powder River Energy Corporation and Basin Electric Power Cooperative on additional grid access for backup service, export capability and future flexibility.
Grid capacity and timing remain subject to utility studies and written confirmation.
| Barber Creek | 1.5 mi |
| Carr Draw | 9.8 mi |
| Pumpkin Buttes | 28.5 mi |
| Identified, Pumpkin Buttes | ~300 MW |
| Indicated, lower voltage | Several 40 MW sites |
About 1,300 MW of thermal generation already operates within 25 miles of the site: Dry Fork Station, Wyodak, Wygen 1, 2 and III, and the Neil Simpson units.
The Energy Park sits between two separately owned 230 kV circuits, and the surrounding network is meshed rather than radial.
| Circuit | Owner | Straight-line distance |
|---|---|---|
| Carr Draw to Barber Creek | Black Hills Power | 0.75 mi |
| Barber Creek to Pumpkin Buttes | PacifiCorp | 0.99 mi |
Circuit geometry, ownership and endpoints from the HIFLD Electric Power Transmission Lines dataset. Distances are straight-line from the Energy Park coordinate to the nearest point on each circuit. Grid capacity and timing remain subject to utility studies and written confirmation.
GridAI is evaluating carbon capture and sequestration at the Energy Park. The current concept places generation, capture and potential injection near the same site. Geology, project design, tax-credit structure and permitting remain under evaluation.
GridAI is also evaluating additional long-term generation technologies for the Energy Park. Gas-fired generation is the initial power platform.
| Gas origin | Biogenic, microbial |
| Stimulation | None |
| Sequestration at the Energy Park | Under evaluation |
| Injection permitting | Not commenced |
Send us the target MW at first energization, ramp schedule, ultimate campus size, target energization date and cooling approach. We will map the generation, gas, water and site plan around it.